Client: BOS Inspection – Root Cause Analysis
Projects Performed: 02
Assam, India
Plant detail: 70 MW / 92 MWp Solar PV Plant,
Client Name: Jakson Power
Sunkonnect deployed a team of Engineers having expertise in Transformer Design and Production to conduct RCA for the failure of a 6.25MVA Inverter Duty Transformer. The team along with the manufacturer performed detailed tests and studies on the transformer leading to the identification of the cause of failure. A detailed report was provided to the manufacturer as well as the client to improve the design and manufacturing of such transformers.